13.70.030 Applicability.
A. A temporary certificate of concurrency issued by the public works department is required for a development permit application to be determined as complete for review by city staff.
B. Per Public Works Development Guidelines and Improvement Standards Manual, Section 11, “Traffic Studies,” a transportation impact analysis will be required for any development that:
1. Generates 50 or more p.m. peak hour project trips; or
2. Generates 40 or more p.m. peak hour project trips if the development:
a. Is near any intersection already experiencing higher levels of traffic congestion and is operating at LOS “E” or “F”;
b. Is near any intersection, arterial, or state highway with known safety or collision history; or
c. Requires access or change to access from a state highway. [Ord. 2013-09-067 § 2; Ord. 2006-04-041].