A. Within 90 days following the date for final compliance by the significant industrial user with applicable pretreatment standards and requirements set forth in this chapter or in a wastewater discharge permit, or within 30 days following commencement of the introduction of wastewater into the POTW by a new source or new users considered by the director to fit the definition of a significant industrial user, the affected user shall submit to the director a report containing the information outlined in BMC 15.14.042(C)(4) through (C)(6).

B. For users subject to equivalent mass or concentration limits established by the director in accordance with procedures established in 40 CFR 403.6(c), this report shall contain a reasonable measure of the user’s long-term production rate. For all other users subject to categorical pretreatment standards expressed in terms of allowable pollutant discharge per unit of production (or other measure of operation), this report shall include the user’s actual production during the appropriate sampling period.

C. In cases where applicable pretreatment standards and requirements include compliance with BMPs, the user shall submit documentation required by the director in the wastewater discharge approval to determine the compliance status of the user. [Ord. 2020-07-016 § 1; Ord. 2019-11-032 § 1].